Wewak Boram Airport in Papua New Guinea

Major upgrade of PNG’s Wewak Airport to start by end of 2026

By Andrew Curran.

A major upgrade of Papua New Guinea’s Wewak / Boram Airport is due to start by the end of 2026, according to the National Airports Corporation. Wewak (WWK) is the latest beneficiary of the country’s programme to upgrade regional airports, officially known as the Civil Aviation Development Investment Project II (CADIP II).

Aero South Pacific’s Wewak / Boram Airport Brief notes that two carriers, PNG Air and Air Niugini, serve the airport from Port Moresby (POM), Vanimo (VAI), Mount Hagen (HGU) and Madang (MAG). The two airlines offer a total of 37 scheduled departures each week.

Currently, Wewak’s 1,600-metre asphalt runway can accommodate PNG Air’s ATR72s and Air Niugini’s Fokker jets. However, the project will see the runway’s length increased to 2,010 metres by extending it towards the south-east.

Other planned work includes pavement strengthening and asphalt surfacing, taxiways, an apron, parking bay areas, a new terminal building and associated infrastructure. The Wewak / Boram Airport upgrade is expected to cost PGK71.96 million (USD16 million) and take two and a half years to complete.

Wewak Airport upgrade will see runway length temporarily trimmed

As with other CADIP II airport upgrades, the runway rehabilitation work will be carried out over approximately 18 months using a staged work plan that allows the airport to remain open during construction. However, from mid-December, the existing runway will have its operational length shortened to 1,400 metres.

Both airlines have, where possible, deployed smaller aircraft to other airports where upgrade work has resulted in reduced available runway lengths. But in some cases, flights have been temporarily suspended.

The aircraft currently operating into Wewak / Boram, typically ATR72s and Fokker jets, will struggle with the new temporary runway length unless they operate with lighter loads.

However, PNG Air has ATR42s and Air Niugini has Dash 8 turboprops, both of which can comfortably land and take off on a 1,400-metre runway. But, as other airports have experienced, further runway shortening can be expected over the course of the rehabilitation work, making life difficult for the airlines and people using the airport.

The National Airports Corporation, which operates Wewak / Boram Airport on behalf of the Papua New Guinea Government, says the runway work will be delivered in ten stages, with each stage progressively upgrading sections of runway pavement and associated airside infrastructure.

“Throughout the duration of the project, Wewak Airport will continue to operate under approved operational arrangements and published NOTAM requirements,” a November 23 statement reads. “These measures will ensure the safe, secure, and efficient movement of aircraft, passengers, and freight while critical infrastructure upgrades are undertaken.”

However, the airport operator acknowledges that the staged rehabilitation work may result in temporary operational limitations during the construction period.

“Working closely with airline operators, aviation stakeholders, contractors, and the CADIP II Project Implementation Unit will be critical to ensuring project activities are carried out with minimal disruption,” the statement adds.

CADIP II airport upgrades are a plus for Papua New Guinea

CADIP II is a USD171.5 million infrastructure programme jointly financed by the Government of Papua New Guinea and the Asian Development Bank to upgrade five major regional airports, four rural airstrips and aviation infrastructure services across the country.

The five-year programme, running from 2023 to 2028, has recently seen the completion of a USD17.3 million upgrade of Alotau / Gurney Airport (GUR) in Milne Bay Province, while rehabilitation work at Aropa / Kieta (KIE), Kiunga (UNG) and Hoskins (HKN) airports has also begun. Wewak / Boram is the fifth of the major regional airports included in the programme.

The current Government is investing heavily in upgrading Papua New Guinea’s aviation infrastructure. Prime Minister James Marape recently said CADIP II would help create the foundations of a modern economy and better connect the country’s citizens.